During April there were a number of developments onsite.
The concreting of the floors was now complete and work begun on inserting the partition walls on each of the three floors.
The steel framework for a walkway has been constructed from the 2nd floor mezzanine across to the tower. The walkway will eventually be turned into a glass walkway creating a bird’s eye view of the reception area below and the west wall stained glass window.
The construction of the lift shaft is complete with mechanisms and fittings to follow during the final stages of the construction program.
The concreting of the floors was now complete and work begun on inserting the partition walls on each of the three floors.
The steel framework for a walkway has been constructed from the 2nd floor mezzanine across to the tower. The walkway will eventually be turned into a glass walkway creating a bird’s eye view of the reception area below and the west wall stained glass window.
The construction of the lift shaft is complete with mechanisms and fittings to follow during the final stages of the construction program.